Yp街机电子游戏

½Ó´ýÀ´µ½Yp街机电子游戏ÍøÕ¾£¬ÎÒÃǽ߳ÏΪÄúЧÀÍ

Ä¿½ñλÖãºÊ×Ò³-×ÊѶÖÐÐÄ>ÐÐÒµÐÂÎÅȼÆø¹ÜµÀ¾¯Ê¾´øµÄ×÷ÓÃ

ȼÆø¹ÜµÀ¾¯Ê¾´øµÄ×÷ÓÃ

ȪԴ£º/ Ðû²¼Ê±¼ä£ºÈÕÆÚ£º2023-05-29 0´Î
µ±¿ªÍÚÊ©¹¤Ê±£¬ÈçÍÚµ½È¼Æø¾¯Ê¾´ø£¬ÔòÌåÏÖÔÚÏ·½0.30.5Ã×´¦ÓÐȼÆø¹ÜµÀ£¬Æðµ½Á˾¯Ê¾ºÍ±£»¤×÷Óá£2¡¢Ê¾×Ù×÷Óá£Ñ°ÕÒµØÂñȼÆø¹ÜµÀʱ£¬ÕÒµ½¾¯Ê¾´ø¼´ÕÒµ½Á˹ܵÀ£¬Æðµ½ÁËʾ×Ù×÷Óá£3¡¢ÏÖÔڵľ¯Ê¾´øÓÐʾ×ÙÏߣ¬Ê¹ÓòâÊÔÒÇÆ÷ÔÚ²»¿ªÍÚµÄÇéÐÎÏ£¬×¼È·Îª¹ÜµÀ¶¨Î»¡£
When excavating and constructing, if a gas warning tape is excavated, it indicates that there is a gas pipeline 0.3 to 0.5 meters below, which serves as a warning and protection function. 2. Tracing effect. When searching for buried gas pipelines, the warning tape is found to locate the pipeline, which serves as a tracer. 3. The current warning comes with a tracer line, which uses testing instruments to accurately locate the pipeline without excavation.
¹µ²Û¿ªÍÚ¡£
Trench excavation.
£¨1£©»ìÄýÍÁ·ÃæºÍÁ¤Çà·ÃæµÄ¿ªÍÚӦʹÓÃÇиî»úÇиî¡£
(1) The excavation of concrete and asphalt pavement should be done using a cutting machine.
£¨2£©¹ÜµÀ¹µ²ÛÓ¦°´ÉèÍýÏ붨µÄƽÃæλÖúͱê¸ß¿ªÍÚ¡£µ±½ÓÄÉÈ˹¤¿ªÍÚÇÒÎÞµØÏÂˮʱ£¬²Ûµ×Ô¤ÁôֵӦΪ0.05~0.10m£»¹ÜµÀ×°ÖÃÇ°Ó¦È˹¤Çåµ×Éè¼Æ±ê¸ß¡£
(2) The pipeline trench should be excavated according to the plane position and elevation specified in the design. When manual excavation is used and there is no groundwater, the reserved value at the bottom of the trench should be 0.05-0.10m; Before pipeline installation, the bottom should be manually cleaned to the design elevation.
£¨3£©¹Ü¹µ¹µµ×¿í¶ÈºÍÊÂÇé³ß´ç£¬Ó¦Æ¾Ö¤ÏÖ³¡ÏÖÕæÏàÐκ͹ܵÀ·óÉèÒªÁìÈ·¶¨¡£
(3) The width and working size of the trench bottom should be determined based on the actual situation on site and the pipeline laying method.
£¨4£©¾Ö²¿³¬ÍÚ²¿·ÖÓ¦»ØÌʵ¡£µ±¹µµ×ÎÞµØÏÂˮʱ£¬³¬ÍÚÔÚ0.15mÒÔÄÚ£¬¿É½ÓÄÉÔ­ÍÁ»ØÌ³¬ÍÚÔÚ0.15,ÒÔÉÏ£¬¿É½ÓÄÉʯ»ÒÍÁ´¦Àí¡£µ±¹µµ×ÓеØÏÂË®»òË®Á¿½Ï´óʱ£¬Ó¦½ÓÄɼ¶Åäɰʯ»ò×ÔȻɰ»ØÌî±ê¸ß¡£³¬ÍÚ²¿·Ö»ØÌîºóѹʵ£¬ÆäÃÜʵ¶ÈÓ¦¿¿½üÔ­µØ»ù×ÔÈ»ÍÁµÄÃÜʵ¶È¡£
(4) Local over excavation should be backfilled and compacted. When there is no groundwater at the bottom of the ditch, if the over excavation is within 0.15m, the original soil can be used for backfilling; If the excavation exceeds 0.15, lime soil can be used for treatment. When there is groundwater or a large amount of water at the bottom of the ditch, graded sand or natural sand should be used to backfill to the elevation. The over excavated part should be compacted after backfilling, and its compactness should be close to that of the original natural soil of the foundation.
£¨5£©ÔÚʪÏÝÐÔ»ÆÍÁµØÇø£¬²»ÒËÔÚÓêÆÚÊ©¹¤£¬»òÔÚÊ©¹¤Ê±ÇÐʵɨ³ý¹µÄÚ»ýË®£¬¿ªÍÚʱӦÔÚ¹µµ×Ô¤ÁôÖµ0.03~0.06mºñµÄÍÁ²ã¾ÙÐÐѹʵ´¦Àí¡£
ȼÆø¾¯Ê¾´ø
(5) In collapsible loess areas, it is not advisable to construct during rainy periods or effectively drain the accumulated water in the ditch. During excavation, a soil layer with a thickness of 0.03-0.06m should be reserved at the bottom of the ditch for compaction treatment.
£¨6£©¹µµ×ÓöÓзÅÆúÐÞ½¨ÎӲʯ¡¢Ä¾Í·¡¢À¬»øµÈÔÓÎïʱ±ØÐ裬²¢Ó¦ÆÌÒ»²ãºñ¶È²»Ð¡ÓÚ0.15mÉ°ÍÁ»òËØÍÁ£¬Õûƽѹʵ¼°Éè¼Æ±ê¸ß¡£
(6) When encountering abandoned structures, hard stones, wood, garbage and other debris at the bottom of the ditch, they must be removed, and a layer of sand or plain soil with a thickness of not less than 0.15m should be laid, leveled and compacted to the design elevation.
£¨7£©¶ÔÈíÍÁ»ù¼°ÌØÊâÇÖÊ´ÍÁÈÀ£¬Ó¦°´Éè¼ÆÒªÇó´¦Àí¡£
(7) Soft soil foundation and special corrosive soil should be treated according to design requirements.
»ØÌîÍÁ¡£
Backfill soil.
£¨1£©²»µÃ½ÓÄɶ³ÍÁ¡¢À¬»ø¡¢Ä¾Áϼ°ÈíÐÔÎïÖÊ»ØÌî¡£¹ÜµÀÁ½²à¼°¹Ü¶¥ÒÔÉÏ0.5mÄڵĻØÌîÍÁ£¬²»µÃº¬ÓÐËéʯ¡¢×©¿éµÈÔÓÎÇÒ²»µÃ½ÓÄÉ»ÒÍÁ»ØÌî¡£¾à¹Ü¶¥0.5mÒÔÉϵĻØÌîÍÁÖеÄʯ¿é²»µÃ¶àÓÚ10%¡¢Ö±¾¶²»µÃ´óÓÚ0.1m,ÇÒÔȳÆÂþÑÜ¡£
(1) Frozen soil, garbage, wood, and soft materials shall not be used for backfilling. The backfill soil on both sides of the pipeline and within 0.5m above the pipe top shall not contain debris such as crushed stones and bricks, and shall not be backfilled with lime soil. The stones in the backfill soil at a distance of more than 0.5m from the pipe top shall not exceed 10%, and the diameter shall not exceed 0.1m, and shall be evenly distributed.
£¨2£©¹µ²ÛµÄÖ§³ÖÓ¦ÔڹܵÀÁ½²à¼°¹Ü¶¥ÒÔÉÏ0.5m»ØÌîÍê±Ï²¢Ñ¹Êµºó£¬ÔÚ°ü¹ÜµÄÇéÐÎϾÙÐвð³ý£¬²¢Ó¦½ÓÄÉϸɰÌîʵÎó²î¡£
(2) The support of the trench should be backfilled and compacted on both sides of the pipeline and 0.5m above the pipe top, and then removed while ensuring safety. Fine sand should be used to fill the gaps.
£¨3.£©¹µ²Û»ØÌîʱ£¬Ó¦ÏÈ»ØÌî¹Üµ×Ðü¿Õ²¿Î»£¬ÔÙ»ØÌî¹ÜµÀÁ½²à¡£
When backfilling the trench, the suspended area at the bottom of the pipe should be backfilled first, and then both sides of the pipe should be backfilled.
£¨4£©»ØÌîÍÁÓ¦·Ö²ãѹʵ£¬Ã¿²ãÐéÆ̺ñ¶ÈÒËΪ0.2~0.3m£¬¹ÜµÀÁ½²à¼°¹Ü¶¥ÒÔÉÏ0.5mÄڵĻØÌîÍÁ±ØÐè½ÓÄÉÈ˹¤Ñ¹Êµ£¬¹Ü¶¥0.5mÒÔÉϵĻØÌîÍÁ¿É½ÓÄÉСÐÍ»úеѹʵ£¬Ã¿²ãÐéÆ̺ñ¶ÈÒËΪ0.25~0.4m¡£
(4) The backfill soil should be compacted in layers, with a virtual paving thickness of 0.2-0.3m for each layer. The backfill soil on both sides of the pipeline and within 0.5m above the pipe top must be manually compacted. The backfill soil above 0.5m above the pipe top can be compacted by small machinery, and the virtual paving thickness of each layer should be 0.25-0.4m.
£¨5£©»ØÌîÍÁѹʵºó£¬Ó¦·Ö²ã¼ì²éÃÜʵ¶È£¬²¢×öºÃ»ØÌî¼Í¼¡£
(5) After the backfilling soil is compacted, the compactness should be checked in layers and backfilling records should be kept.
¾¯Ê¾´øÆÌÉè¡£
Warning tape laying.
£¨1£©ÂñÉèȼÆø¹ÜµÀµÄÑØÏßÓ¦Ò»Á¬ÆÌÉ辯ʾ´ø¡£¾¯Ê¾´øÆÌÉèÇ°Ó¦½«ÆÌÉèÃæѹʵ£¬²¢Æ½ÕûµÄÆÌÉèÔڹܵÀµÄÕýÉÏ·½£¬¾à¹Ü¶¨µÄ¾àÀëÒËΪ0.3~0.5m£¬µ«²»µÃÆÌÉèÓÚ·»ùºÍ·ÃæÄÚ¡£
(1) Warning tapes should be continuously laid along the buried gas pipelines. Before laying the warning tape, the surface should be compacted and laid flat above the pipeline. The distance from the pipeline should be 0.3~0.5m, but it should not be laid in the roadbed or road surface.
£¨2£©¾¯Ê¾´øÒ˽ÓÄÉ»ÆÉ«¾ÛÒÒÏ©µÈ²»Ò×ÆÊÎöµÄÖÊÁÏ£¬²¢Ó¡ÓÐÏÔ×Å¡¢Àο¿µÄ¾¯Ê¾Ó×ÖÌ岻ӦСÓÚ100*100mm¡£
(2) The warning tape should be made of materials that are not easily decomposed, such as yellow polyethylene, and printed with clear and firm warning messages. The font should not be less than 100 * 100mm.
±¾ÎÄÀ´×Ô:ȼÆø¾¯Ê¾´ø¸ü¶àµÄÄÚÈÝÇë»÷:ÎÒÃǽ«»áΪÄúÌáÎʵÄÎÊÌâÌṩһ¸öÖª×ãµÄЧÀÍ£¬½Ó´ýÄúµÄÀ´µç£¡
This article comes from: Gas warning tape. For more information, please click on: We will provide a satisfactory service for the questions you ask. Welcome to call us!

Ïà¹Ø²úÆ· / Related products

  • µØ¶¤

    µØ¶¤

  • µØ¶¤

    µØ¶¤

  • ¾¯Ê¾×®

    ¾¯Ê¾×®

  • ¾¯Ê¾×®

    ¾¯Ê¾×®

½ØÆÁ£¬Î¢ÐÅʶ±ð¶þάÂë

sitemap¡¢ÍøÕ¾µØͼ